CATAWBA COUNTY PERMIT DETAIL REPORT
|
|
|
|
|
|
|
|
|
|
CONTACT LIST
GENERAL INFORMATION
LIEN AGENT ENTRY NUMBER:
PROPERTY ID#:
STREET ADDRESS:
|
|
PROJECT:
PROJECT DESCRIPTION:
40 Re-heat coils, 2 mini splits, & 11 fans / The work will be completed in three primary phases Phase 1:the laboratory department will be constructed in the 4th floor shell space 6,273 SF and relocated from its 1st floor location Phase 2: the existing vacated lab space (6,499 SF) will be renovated to expand the existing emergency department, Phase (3) renovations and upgrades to finishes in the existing emergency department (12,075 SF)
APPLIED:
EXPIRES:
ISSUED:
|
|
|
STATUS:
|
TOTAL SQ FT
TYPE OF USE:
WORK CLASS:
|
|
|
RELATED_PERMIT#
WORK CLASS
STATUS
ISSUED
FINALED
|
|
|
|
|
RELATED PERMITS
PLAN CASE
STATUS
COMPLETED
WORK CLASS
DISTURBED ACRES
|
|
|
|
RELATED PLAN CASES
ACTIVITIES
INSPECTION HISTORY
SCHEDULED
COMPLETED
STATUS
INSPECTION TYPE
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CATAWBA COUNTY PERMIT DETAIL REPORT
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Final this case.
NOTE: This Inspection was for the 2nd half of the new Emergency Room. This half is the front section for entrance.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
This Inspection was for a Partial of the new Emergency Room as highlighted on the Approved Plans, Sheet A1.1n in Yellow, marked DLC; JM;BH;GC, dated 5/16/18.
Permit to remain open for futher work of the Emergency Room .
|
|
|
|
|
|
|
This Inspection Was not an Above Ceiling Mech., but rather a DUCT/SEAM SEAL Inspection.
This Inspection was part of the front ER section...main level..Rooms 144c, 149, 117, 151, 152, 153, 154, 155, 170a,b,c, 170, 171, 173, 165, 196
|
|
|
|
|
|
|
|
|
|
|
|
|
This Inspection today approves Phase 2 of the new ER.....Permit is to remain open for futher phases of this same project.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
This Inspection covers up to Room 109. South of Room 109 is not ready.
NOTE: This is PHASE 2
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CATAWBA COUNTY PERMIT DETAIL REPORT
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
This Inspection APPROVES the First floor---Phase 1---Morgue and Ultra Sound....AND...Approves a Temporary "CO" for use of these sections.
NOTE: ALL Permits are to remain open for future Phases of work completions.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
NOTE: This Inspection WAS NOT a "Rough Mechanical", but rather an "DUCT SEAM/JOINT SEAL" inspection. Please call in for the correct Inspection titles in order to keep our Inspection Records in order.
This Inspection approves the Duct Seam/joint Seal for the Fourth Floor Lab. This Inspection does not cover the Corridor areas at this time.
|
|
|
|
|
|