Image

CATAWBA COUNTY PERMIT DETAIL REPORT

BUILDING (C)
Alteration
Architect
*RAY CAMPBELL DESIGN, 29 S COLLEGE AVE, NEWTON NC 28658
Billed To
*CAMPBELL DESIGN (BILLING ONLY), 29 S COLLEGE AVE, NEWTON NC 28658
Contact Person
JOHN CAMERON, 434 3RD ST NE, HICKORY NC 28601
Lien Agent
NO LIEN AGENT REQUIRED, , 
Owner
CATAWBA COUNTY, PO BOX 368, NEWTON NC 28658-0368
Contractor

CONTACT LIST

GENERAL INFORMATION

CENSUS TRACT:

011200

LIEN AGENT ENTRY NUMBER:

PROPERTY ID#:

STREET ADDRESS:

25 GOVERNMENT DR, NEWTON NC 28658

GIS

0

PROJECT:

PROJECT DESCRIPTION:

Interior alterations to one suite on each floor, no plumbing work to be done.

APPLIED:

EXPIRES:

ISSUED:

09/13/2018
09/13/2018
03/17/2020

STATUS:

Final

TOTAL # OF ROOMS:

NUMBER OF UNITS:

VALUE:

CODE EDITION:

ZONING:

# OF STORIES:

TYPE OF USE:

TOTAL SQ FT

 0
 0
$119,000 
 0
Business
IBC 2012
1

RELATED_PERMIT#

WORK CLASS

STATUS

ISSUED

FINALED

ELEC-09-2018-105408
Alteration
Final
09/13/2018
04/01/2019
MECC-09-2018-105611
Alteration
Final
09/18/2018
04/01/2019
PLMC-12-2018-109257
Alteration
Final
12/14/2018
04/01/2019

RELATED PERMITS

PLAN CASE

STATUS

COMPLETED

WORK CLASS

DISTURBED ACRES

Approved
08/01/2018
Building Alteration
N/A

RELATED PLAN CASES

ACTIVITIES

INSPECTION HISTORY

SCHEDULED

COMPLETED

STATUS

INSPECTION TYPE

Building Final
Jarrett Miller
04/01/2019
Approved
(828)639-0961
04/01/2019
Framing Above Ceiling
Jarrett Miller
03/14/2019
Approved
(828)639-0961
03/14/2019
Rough Building
Jarrett Miller
02/15/2019
Approved
(828)639-0961
02/15/2019
Image

CATAWBA COUNTY PERMIT DETAIL REPORT

Building Final
Craig Taylor
01/02/2019
Follow Up Required
(828)639-0396
01/02/2019
Other Inspector Comments
Phase 2 only, will need to schedule another final for 2nd floor when ready.
Rough Building
Jarrett Miller
12/13/2018
Approved
(828)639-0961
12/13/2018
Other Inspector Comments
Second floor
Building Final
Jarrett Miller
11/21/2018
Follow Up Required
(828)639-0961
11/21/2018
Other Inspector Comments
Basement area only, will need building final for second and third floor once ready
Framing Above Ceiling
Garry Cornell
11/16/2018
Approved
(828)217-0490
11/16/2018
Rough Building
Jarrett Miller
10/26/2018
Approved
(828)639-0961
10/26/2018
Other Inspector Comments
Studs in EHC and old veterans affairs
E9 - rpermitdetail
Page 2 of 2